OWA CUT & CAP PROGRAM LLOYDMINSTER | PROVOST 2026

ProFoxx Asset Retirement Management
Cut & Cap Program

Lloydminster & Provost areas · Anticipated start October 1, 2026. A line-item pricing response from Innovative Well Abandonment and Competition Well Services, structured to ProFoxx's scope exactly as requested.

95
Wells
Cut & cap scope
2
Crews at Peak
Ramping from 1 at start
Oct 1
Mobilization
Anticipated 2026 start
Sep 3
Pricing Due
To ProFoxx, 2026
01 — Program Footprint

Lloydminster & Provost

095
Wells
Cut & cap scope
02
Crews at Peak
Ramping from 1 at start
Program Timeline
Sep 3 · Pricing DueOct 1 · MobilizePre-Winter Close-out
1 Crew · Week 12 Crews · Week 2 Onward
Operating entirely under the Alberta OWA program through ProFoxx Asset Retirement Management.
02 — Vendor

Innovative Well Abandonment

Equipment, experience, and safety systems behind the program.

Equipment

  • Ultra-high pressure water jet cutting truck
  • Case 590, rubber tire backhoe
  • Crew truck + Dump Trailer
  • 1MM BTU Steamer Systems Onboard
  • Dual Intensifier Pumping System

Experience

  • 17K+ Abandoned Wells Cut & Capped
  • 3,735 Piles Cut
  • 735+ Risers Removed
  • 15yrs+ Industry Experience

Safety & Systems

  • TRIF of 0
  • Comply Works
  • ISN
  • AVETTA
  • 8AM Solutions
  • SECOR

Compliant on

WorkHubCOR Workplace SafetyISNetworldComplyWorksAvettaWorkSafeBCWorkHubCOR Workplace SafetyISNetworldComplyWorksAvettaWorkSafeBC
03 — Field Requirements

Documentation & Invoicing Protocol

Every requirement in the ProFoxx scope, built into daily field execution.

1

Sitewide Daily Photo Record

End-of-day pictures for every wellhead cut and removed, filed per well, signage, centralizer, casing, backfill.

2

Field Tickets

Each ticket clearly identifies the wells completed and all applicable charges.

3

Approved & Stamped

No invoicing until field tickets are approved and stamped in the field.

4

OpenInvoice Submission

Invoices submitted directly to OWA through OpenInvoice.

HSE Verification

Safety pre-qualification, SECOR, insurance, and orientation packages confirmed.

Legal Authorization

Master service agreements, OWA program acknowledgements, and site access.

Financials

OpenInvoice onboarding with fixed-timeline pricing — no budget surprises.

Pricing Submission Deadline
Final rate sheets due to ProFoxx
September 3, 2026
04 — Differentiator

The Strategic Edge: IWA Partnership

Side-by-side: how IWA reframes a standard cut and cap engagement.

05 — Pricing

Rate Schedule

Structured line-for-line against the ProFoxx pricing request.

Cut & Cap
$800/ WELL

Regardless of casing or wellhead size.

  • Minimum productive field time10 hrs / day
  • Excludes travel to first & from last well
  • Target output~12 wells / day
Casing Cutting & Removal
$450/ HR
Travel
  • Crew & equipment$375 / hr
  • Crew truck mileage$1.50 / km
Mobilization
  • Crew 1 — Lloydminster based (local)No charge
  • Lloydminster to Provost$750
  • Crew 2 — Edmonton to Lloydminster / Provost$1,500
Wellhead Removal & Transport
$500/ DAY + $1.50 / KM

Cut wellheads moved to the steel-field dumpster.

Standby / Regulatory Delay
  • On-site delays outside crew control$450 / hr
  • Second crew standby$2,500 / day
Safety
Included
Overtime
No Overtime

No overtime is applicable for this project. Standard day covers daylight operating hours only.

Living Costs
  • Crew 1 (local)No subsistence
  • Crew 2 subsistence$50 / person / day
  • Crew 2 accommodation$175 / person / day
Mobilization Origin: Crew 1 mobilizes locally from Lloydminster.
All rates quoted without a fuel surcharge, per OWA direction.
06 — Conditions

Assumptions & Qualifications

Stated up front so the final cost carries no surprises.

Fuel Surcharge

No fuel surcharge applied. Rates are quoted all-in, consistent with OWA's request to remove surcharges.

Site Condition Assumptions

Sites are prepped and accessible ahead of the crew —  any line locates or ground disturbances permits are in place, and lease access maintained for equipment and crew.

Worktime Hours

IWA requires a minimum of 10 hours of productive field time. With travel to the first site and the last site outside of the 10-hour working time.

No Overtime

No overtime is applicable for this project. The standard day is based on daylight operating hours; hours beyond the standard day are not billed at an overtime rate.

Two-Crew Ramp

Pricing assumes one cut and cap truck/crew at start-up, scaling to two crews approximately one week into the program to complete the work ahead of winter conditions.

Standby & Weather

Standby applies for client-caused delays, wet or frozen access, and regulatory holds outside our control, billed hourly per crew.

07 — Contacts

Leadership & Next Steps

Prime Contractor

ProFoxx Asset Retirement Management

TD
Trevor Dziaduck
Account Operations Manager
WH
William Hewitt
CEO | President
Proposal Leads

Innovative Well Abandonment

SB
Scott Bowes
Primary Contact / President
CH
Chris Hamilton
Secondary Contact / Business Development Manager
Submitted To

ProFoxx Asset Retirement Management

Trevor Dziaduck
Account Operations Manager
(403) 437-1424trevordziaduck@profoxxarm.com
www.profoxxassetretirement.com
Action Required

Submit final rate sheet to ProFoxx

By September 3, 2026

Contact Scott Bowes